PAS 2035:2023 is the current edition of the retrofit process standard. Its foreword says it supersedes PAS 2035:2019+A1:2022, which was withdrawn on 30 March 2025. For a heat pump installer the practical questions are narrower than the standard: which role you hold on a PAS 2035 project, what a retrofit assessment gives you, and which rules of your own still apply in full. Clause numbers below are from the PAS 2035:2023 text.
What PAS 2035:2023 covers
The full title is "Retrofitting dwellings for improved energy efficiency. Specification and guidance". Clause 1 gives its scope as assessment of dwellings, identification and evaluation of improvement options, design and specification, and monitoring and evaluation. Installation is in PAS 2030. Among the changes the foreword lists for the 2023 edition are an airtightness strategy for each project, a medium-term improvement plan that is now a requirement, Annex C brought in line with the current Approved Document F, and a route by which the distressed replacement of a heating appliance can comply after the event.
BSI's product page mentions limited transition arrangements for some funded projects. If you are finishing work that started before 30 March 2025, ask the scheme administrator which edition the project is held to, and get the answer in writing.
The roles, and where the heat pump designer fits
Every domestic retrofit project shall be coordinated by a Retrofit Coordinator (6.1.1), involved from before the assessment to the end (6.1.5). The coordinator agrees and records the intended outcomes with the client at the start (6.2.1) and, if employed by a firm doing the assessment, design or installation, must declare that to the client (6.1.4). Annex A sets the qualifications.
| Role | What it does | Qualification in Annex A |
|---|---|---|
| Retrofit Coordinator | Oversees the project from assessment to evaluation | Level 5 Diploma in Retrofit Coordination and Risk Management, or working towards it (A.2.1) |
| Retrofit Assessor | Carries out the whole-dwelling assessment | Registered domestic energy assessor or RICS surveyor, plus a Level 3 older buildings award for traditional construction (A.1) |
| Retrofit Designer | Prepares the retrofit design | For a single measure in MCS scope, an MCS certified designer or a chartered building services engineer (A.3.4) |
| Retrofit Evaluator | Monitors and evaluates the project | A qualified Retrofit Coordinator (A.4.1) |
One person can hold several roles if qualified for each and any conflict of interest is reported to the client (A.5). Two clauses settle the heat pump's place. A retrofit design that includes systems covered by MCS shall specify that they comply with the relevant MCS standards (8.2.22). Their installation, with associated components and controls within MCS scope, follows those MCS standards instead of PAS 2030 (9.1). On a project with several measures, ask the coordinator who holds design responsibility for the heat pump and who for the fabric.
What the whole-dwelling assessment records
Clause 7.3.2 lists what the Retrofit Assessor collects. These are the parts a heat pump designer will use most.
- The construction of the main elements, with U-values and moisture properties (g). A note warns that RdSAP default U-values might not suit traditional buildings.
- A measured survey of the heat loss envelope, every element and every opening (h).
- The installed heating, hot water and ventilation, with their age, service history and whether they work (j).
- An inspection of existing ventilation against Annex C, recording every fan by type and model and the size and position of every background ventilator (f).
- Occupancy, including vulnerable occupants (k), and any defects, damp and mould (d).
The data are used to estimate annual fuel use, costs and emissions with a recognised model such as RdSAP, SAP or PHPP (7.3.3). The report goes to the Retrofit Designer with the data file and photographs (7.4.1), and sorts defects into those that must be repaired before retrofit and those only recommended (7.4.2). It is a useful input. It is not a room-by-room heat loss calculation.
A distressed heating replacement
When a heating appliance fails and is replaced in a hurry, PAS 2035:2023 accepts that the assessment and the coordinator may come later. The whole-dwelling assessment is completed as soon as possible during or after the work (7.2.1), the design follows a short list of clauses (8.3.1), and once a coordinator is involved the rest of clause 8 applies. If nothing else is installed, the minimum output is the improvement options evaluation and the medium-term improvement plan (8.3.2).
BS 40104:2025 covers the retrofit assessment
BS 40104:2025, "Retrofit assessment for domestic dwellings. Code of practice", was published on 24 September 2025. BSI's page says it covers the dwelling's context, condition, ventilation, occupancy, energy performance and site considerations, with assessor competence, reporting and lodgement, and excludes fire, gas, electrical and structural evaluation. A scheme may name BS 40104, PAS 2035 or both, so check its guidance.
Funding schemes set the requirement
Whether a job must follow PAS 2035:2023 is set by each funding scheme's rules, so ask for the scheme guidance or the managing agent's contract in writing before you price.
In October 2025 the government decided to make MCS the only certification scheme for low-carbon heat measures under the Boiler Upgrade Scheme, ECO4, the Warm Homes: Social Housing Fund and the Warm Homes: Local Grant, removing the 'or equivalent' option (government response). The Boiler Upgrade Scheme guidance already requires MCS certification. MIS 3005-D:2025 and MIS 3005-I:2025 do not mention PAS 2035. On a job where the scheme requires both, you answer to both.
ECO4 is due to end on 31 December 2026, with no successor supplier obligation. The Warm Homes Plan says the Local Grant and the Social Housing Fund will merge into one low-income scheme from 2027/28. Grant funding for installers covers the schemes.
Your heat load still describes the house as it will be
The heat load calculation is yours. MIS 3005-D:2025 §3.4.1(a) (Issue 3.0 §5.5.1(a), December 2025) requires a calculation to BS EN 12831-1:2017, and the assessment does not replace the room-by-room method.
PAS 2035:2023 has the retrofit design specify the sequence of installation (8.2.24), so ask for it. Insulation, glazing or airtightness work may come before, alongside or after the heat pump. A heat load worked out on the house as surveyed will be too high if the walls are insulated a month later, and one that assumes insulation will be too low if that measure is dropped. The CIBSE and HPA UK Domestic Heat Pump Design and Installation Guide (2026, note 113) makes the same point from the survey side: record each fabric improvement, discuss it with the client, and explain that doing it first can mean a smaller system. State in your design which fabric condition you assumed and who confirmed it. Fabric first or heat pump first goes through the sizing consequences.
Ventilation changes reach your numbers too. Annex C can require continuous mechanical extract or heat recovery ventilation when the fabric work is extensive, and that changes the ventilation heat loss. Ventilation when upgrading fabric covers it.
What to ask before you price a funded job
- Which scheme funds the work, and which edition of which standard its guidance names.
- Who the Retrofit Coordinator is, and who holds design responsibility for the heat pump.
- Whether you can have the assessment report and data file, and to which standard it was done.
- Which fabric and ventilation measures are confirmed, and the installation sequence in the retrofit design.
- Which certifications the scheme expects of you. PAS 2035:2023 sends MCS-scope work to the MCS standards, but a scheme can ask for more.
The homeowner's side of this is in planning a whole-house retrofit.